City of Saline WWTP Odor Project Update

City of Saline WWTP Odor Project Update

The project remains on schedule for the WWTP odor control system to be completed in spring 2019.  Work is being performed daily at the WWTP.  October will see most or all of the concrete foundations completed.  Through the winter months, the contractors will assemble duct supports and ducts to collect the odorous air and deliver it to the odor control units.  The odor control treatment units have been ordered and will be manufactured over the winter months for delivery in the spring.

Work continues at the Southside Pump Station.  The odor control unit there is smaller and the manufacturing time is shorter.  The contractor is anticipating on having the Southside Pump Station odor control system operating on or before January 1, 2019.

Work also continues at the Sauk Trail Business Park generator and the WWTP flood pump.  Those parts of the project are scheduled for completion this fall and winter.

Please contact Steve Wyzgoski, WWTP/WTP Superintendent with questions at 734.944.2003.